‘JUNITRAN’ RESEARCH CENTER
TECHNICAL OFFER
High-Speed String Transport
Line
"Beijing - Hongkong
(the Island of Taiwan)”
Gomel 1997
TECHNICAL OFFER
High-Speed String Transport Line
"Beijing-Hongkong (Taibej)” (3,140 km)
1. String Transport System
1.1. Principal Route Diagram
The String Transport System (STS) is a string rail route to carry
electrical wheel vehicles. A specific feature of the route are the strings
within the rails stretched to the total force 250 tf per rail. The strings
are rigidly secured to anchored supports spaced every 500...2000 m, the
route structure being carried by intermediate supports spaced every 10...100
m. The strings are arranged within the rails having a deflection of several
centimeters increasing to the span center and reducing to zero over the
supports. Hence, the rail head supporting the vehicle wheel statically
has no deflection or joints throughout its stretch. While remaining highly
straight and rigid the STS rigid structure promises to allow speeds of
350...400 km/h and more in future. The design, technological and other
STS features are demonstrated in more detail in [1].
An international invention application “Linear Transport System”
has been filed under # PCT/IB94/00065 dated 08.04.94 under which an international
patent search has been accomplished, it has undergone expertise and initial
patents have been obtained in the Russian Federation and the South African
Republic (the patenting is underway in 20 countries).
1.2. Line Route Diagram
Fig. 1 shows the route line diagram. The optimum spacing between
intermediate supports is 25 m. This spacing can be reduced to 10 m along
the stretches with more intricate profiles or increased to 100 m. When
the spacing is larger (the modern materials allow to have the spacing 2,000
m and more) the route structure will be supported with ropes or cables
(like suspended bridges).
Considering that the STS is easily adaptable to the terrain profile
the intercity line can run along the shortest cuts or straight. When necessary,
the route structure can be curved in both vertical and horizontal planes.
For comfort (so that passengers are not affected by overloading along curved
stretches) the curvature radii should be at least 10 thous.m.
The stretch of the overland portions of the route will amount to
3,000, out of them 2,930 km will run over the territory of mainland China
and 70 km over the island of Taiwan.
The stretch of the sea portion of the route will amount to 140 km.
It will run over the bottom of the Taiwan Straight (the depth is up to
100 m, the average depth is about 50 m). The STS sea portion will run along
three tunnels 320 cm in diameter each (direct, return and emergency lines)
arranged on the sea bottom surface, with individual portions 0...10 m under
the bottom. The tunnels will be covered with a soil layer to exclude exterior
damage.
1.3. Route Structure
Depending upon the span the STS structure is divided into two typical
types (Fig. 1): I - common design ( the span is up to 100 m); II- additional
supporting cable structure (the span is over 100 m) with the cable arranged:
(a) underneath; (b) above with parabolic deflection (c)
above as guy ropes. The STS structure sea portion in the tunnels will be
according to type I.
The stretch of the overland portions of the route will be 3,000 km,
out of them 2,930 km over the territory of mainland China and 70 km over
Taiwan.
The stretch of the sea portion will be 140 km. It will pass along
the bottom the Taiwan straight (the depth is up to 100 m, the average is
about 50 m). The STS will be run along three tunnels 320 cm in diameter,
each (direct, return and emergency lines disposed on the bottom surface
or made 0...10 m deep under the bottom. The tunnels will be covered with
a soil layer to exclude external damage.
1.3.1. Rail-String
Fig. 2 shows the rail-string design. Each rail head is a current
carrier electrically
insulated from the carrying structure and other supports and rails.
Each rail has three strings of wires 1...3 mm in diameter stretched with
the total force 500 tf for the route structure and 1000 tf for the double-track
route. The wires in the string are encapsulated in a protective sheath
between the supports, they are not linked together being arranged in a
special corrosion resistant composition. The strings are rigidly secured
in the anchored supports. The strings will be anchored to the walls of
the tunnels along the sea portions. A modular design of the rail has been
developed for reducing consumption of materials and facilitating their
fabrication and erection. The rail design is described in more detail in
[1].
1.3.2. Carrying Cable
Like the strings in the rail, the carrying cable is made from heat
resistant steel wires enclosed into a protective watertight sheath. The
free space in the cable is filled up with a corrosion resistant filler.
The longer the span the greater is the cable diameter. For example, due
to a low material consumption for the route structure and its light weight,
the cable 100 mm in diameter carries the STS span 500...1000 m long, i.e.
it allows to cross wide rivers in a single span.
1.3.3. Route Structural Rigidity
The STS route structure requires little material, about 100 kg/m,
still allowing to achieve a highly strong tensioning of the strings. It
has a typical small deflection of the structural elements both under its
own weight (see Table 1) and under the weight of moving vehicles.
Table 1
Deflection of the STS Structure under its Own Weight
|
|
Static (erection) deflection of structural elements
|
|
Span, m
|
string in rail
|
guy cable
|
|
|
Absolute deflection, cm
|
Relative deflection
|
Absolute deflection, m
|
Relative deflection
|
|
25
|
1,6
|
1/1600
|
-
|
-
|
|
50
|
6,3
|
1/800
|
-
|
-
|
|
75
|
14,1
|
1/530
|
-
|
-
|
|
100
|
25
|
1/400
|
0,25
|
1/400
|
|
250
|
-
|
-
|
1,56
|
1/160
|
|
500
|
-
|
-
|
6,25
|
1/80
|
|
750
|
-
|
-
|
14,1
|
1/53
|
|
1000
|
-
|
-
|
25
|
1/40
|
The deflection figures in Table 1 determine the height of the STS
spans, their sliminess and aesthetic appearance. In any case, the STS structure
is much slimmer than bridges, road arteries, viaducts and other similar
structures of highways and railways or girders of monorails.
The strings will have a deflection after erection concealed within
the rail. When the span is 25...50 m the string will have the relative
deflection 1/1600...1/800 and absolute deflection 1.6...6.3 cm in respect
to the span. This deflection is easily accommodated within a specially
designed rail 20...25 cm high.
In any case, the above deflections appear after erection without
affecting the smoothness of rail heads which are very rectilinear when
unloaded. The route curvilinearity in the vertical plane appears under
a moving load, it is induced by winds and moving vehicles in the horizontal
plane. The maximum static deflection produced by a vehicle (2,500 kgf)
braked in the span center will be within 1/800 for the rail and 1/2400
for the span supported by the cable. Dynamic deflections at speeds over
200 km/h will be significantly less than those indicated above (within
1/10,000...1/2,000, or within 5...10 mm in absolute figures for a 25-m
span). These figures prove that the STS is more rigid (in respect to the
rolling stock) than railways, bridges and highway loops which have a greater
estimated deflection under nominal loads.
The structural features of the route and the modes of movement of
the vehicles have been investigated and designed so as to eliminate resonance
phenomena in the rail-string. Moreover, appearing vibrations will remain
behind a moving vehicle, they will attenuate within 0.1...0.5 s, consecutive
vehicles will run along undeflected, perfectly smooth rails.
Variations of temperature-induced deformations of rail-strings are
compensated by temperature strains, hence, variations of the span relative
deflection will insignificantly affect the route’s rail-string smoothness
when the span between the anchored supports remains unchanged. The string
will not have any deformation seams along its stretch, it will respond
to temperature variations like a telephone wire or a power transmission
line which are also suspended with deflection between supports without
joints for several kilometers, like the strings in the rail. The maximum
temperature variations for 100oC, for example, -50oC
(winter) to +50oC (summer) will cause relative deflection variations
within 1/10,000 basically without any effect upon the route smoothness.
Elongation strains in the string will add approximately 500 kgf/cm2
in the summer and deduct the same 500 kgf/cm2 in the winter.
A smaller temperature difference, for example, along the sea portion arranged
in the tunnel, will produce a milder strain deformation of the rail-string.
Taking into account a highly streamlined design of the STS and the
vehicles, the relative deflection of the STS route overland structure under
the influence of lateral winds blowing with the speed 100 km/h will amount
to 1/10,000...1/5,000 without any significant effect upon the transport
line's performance.
The route's smoothness will not be affected by the ice appearing
on the STS structural elements at negative air temperatures. Yet, considering
the rail-string small cross section, the
streamlined design, high- and low-amplitude vibrations and other
factors inhibiting icing, the latter can be fully eliminated. For example,
special modules equipped with gas turbine engines can be sent regularly
to melt ice film with hot air stream along the route during the most risky
winter periods.
1.4. Supports
The carrying structure of the supports comprises two basic
types: (a) the anchored supports to undertake horizontal forces produced
by string and cable elements; (b) carrying supports to undertake just the
vertical load of the STS route structure and vehicles.
The anchored supports can be spaced at 0.5...2 km (the optimum overland
span is one km), depending upon the terrain relief. The maximum horizontal
loads experienced just by the terminal anchored supports (they are affected
by one-way loading) are: 1,000 tf for the double-track and 500 tf for the
single-track routes.
The intermediate anchored supports (they comprise over 90% of the
total number) will not experience any significant horizontal load in operation,
because the forces acting upon the support from each side will become mutually
balanced. In accordance with the terrain relief the carrying supports will
be spaced at 10...100 m overland (the optimal span is 25 m) and at 10 m
along the sea portion (in the tunnel). The minimal vertical load upon the
support (together with the moving vehicle weight) is 10 tf (the span is
10 m), the maximum load is 35 tf (the span is 100 m).
The terrain relief and the longitudinal route profile and the layout
will determine how tall the supports should be. Table 2 is a guide for
practically any terrain relief showing that they should be 15 m tall, on
the average.
Table 2
Determination of Average Tallness of Supports
|
Tallness of supports, m
|
Proportion of the supports in their total number, %
|
|
10
|
70
|
|
20
|
20
|
|
30
|
5
|
|
40
|
3
|
|
50
|
1.5
|
|
100
|
0.5
|
|
Total: average tallness of supports -15 m
|
100
|
The supports are described in more detail in [1].
The alternatives of one-track STS routes and their supports to suit
various geographic conditions are shown in Fig. 4-7.
The carrying supports experience slight vertical, transverse and
longitudinal loads (for example, the transverse loads appear during braking,
they are transmitted by the rail-strings to the anchored supports. Therefore,
the supports have typically small cross-sections, light foundations, they
occupy little area and require little earthwork. It is specifically significant
not to encroach upon the proprietary rights of land owners which may create
serious problems. The STS can be run in a single span (up to 2,000 m long)
50...100 m high over expensive land plots with economical land use. Since
the STS is a "transparent" structure (almost without shadow)
it will be ecologically clean, with a low noise level, it can run over
residential areas, game preservations, parks, etc.
Designs of unified modular STS supports have been developed: short
(5...15 m), average (15...25 m), tall (25...50 m) and supertall (50...100
m) which are unique in their little consumption of materials and they are
highly easy to fabricate and erect.
1.5. Vehicle
The passenger vehicle accommodates 10 persons (during peak hours),
a cargo vehicle can carry 4,000 kg load, the motors are 80 and 40 kW, respectively,
with the energy delivered through wheel which contact the current conducting
rail heads (the right and the left) allowing to reach the speed 300 km/h.
The drive can be designed as two motor wheels 40 kW each. A perfect shape
of the vehicle body has been selected with the aerodynamic resistance factor
Cx=0.075 (the model was tested in the aerodynamic
tube) allowing to minimize the aerodynamic losses and noise at high speeds.
To reach 400 km/h the power of the motor of the passenger vehicle should
be increased to 200 kW and to 400 kW to reach 500 km/h. For the cargo vehicles
to reach the same speeds it is enough to have a motor which is twice less
powerful than that of the passenger vehicle (the front surface area of
the cargo vehicle is two times less)
The vehicle can operate as a routed taxi from the boarding station
to the destination without any driver being steered by the on-board computer.
The latter is controlled and guided by line computers and central computers.
The vehicle is described in [1] in more detail.
1.6. Passenger, Cargo Terminals and Stations
Terminals will be circular with moving (rotating) platforms (Fig.
3) or floors. The terminal diameter is about 60 m which can be increased
up to 100 m or more where passenger traffic is heavier (over 100 thous.
passengers during 24 h).
Intermediate stations with significant passenger traffic will have
switches and sheds to pass the vehicles irrespective of the main schedule
(Fig. 1). The stations with lighter passenger traffic are made as open
platforms along the route.
The boarding (landing) of passengers is effected after braking individual
vehicles with vacant seats. The route is designed to have 17 terminals
and 15 stations.
Circularly shaped cargo terminals will be equipped to load and unload
automatically cargo modules. They will be compact with extensive handling
facilities employing a unique process of handling operations and specially
designed containers for fluid, bulk and piecemeal cargo. For example, a
terminal 100 m in diameter will be capable to handle about 100 thous. tons
of oil (or oil products) a day (36.5 mln tons a year) or much smaller in
size than a sea harbor of the same handling capacity.
Individual consignments, such as passenger cars, can be transported
on open platforms, though it may require to increase the power of the motor
of a cargo module 3...5 times. Thus, passengers can cross the sea without
leaving their cars.
1.7. Management of Passenger and Cargo Traffic
1.7.1. Boarding and Landing
Upon entering into the terminal the passenger sees a lighted sign
on each vehicle (the sign can either be on the vehicle wall or on the terminal
wall as a running string of information) indicating the destination name,
for example, "the terminus". If the required destination is not
indicated the passenger can board a vacant vehicle and press the "terminus"
button (inside the vehicle). Passengers will have 0.5...2.5 min to board
if the moving platform with the vehicle on it has the speed 0.5 m/s and
the circular route is 50 m in diameter. After the door is shut (automatically
or manually) the vehicle is released from the moving platform, the switch
transfers it to the track line. In case the door has not been shut or the
boarding has not been completed or there are no passengers the vehicle
is returned to the second round on the platform. Similarly the passengers
land at their destination in reverse order. In its general implementation
it resembles the handling of baggage along circular conveyers at modern
airports. If necessary, some vehicles may be directed to workshops in a
separate building or at another floor of the terminal.
1.7.2. Cargo Handling
Cargo is handled automatically at cargo terminals. Consignments
are delivered to the terminal and thence to a consignee by other means,
such as an oil pipeline Large consignees and consignors, such as oil refineries,
will have their own terminals.
Full containers are loaded into the cargo modules which are then
marshaled into trains and directed to the transport line. At destinations
containers are removed from modules and directed for unloading, their places
are occupied by empty containers or containers with other cargoes. The
capacity of a container is 1000...4000 kg. Each container is accompanied
with an electronic card to be read by the on-board computer to enter the
nature of a consignment, its weight, conditions of transportation, destination,
consignee, etc.
Passengers can continue to travel in their cars on a special open
platform or they can commandeer to dispatch their cars ahead of them or
to follow them in an open cargo module and travel in the passenger vehicle.
1.7.3. Traffic
Vehicles are grouped together electronically, for example, into
trains of five vehicles with the space between them 100...500 m. The control
system along the entire route maintains the same speed of the vehicles
in the train and the spacing between them. To maintain the traffic of 1,000
passengers per hour one train of five vehicles should leave the terminal
every three minutes. The average spacing between the trains will be 14
km at a speed of 300 km/h. This spacing is sufficient for maneuvering when
passengers board or land at intermediate stations. The running trains will
be grouped at boarding stations and by adding vehicles at intermediate
stations (at the head or at the tail). Therefore, the control system will
both send vehicles and control their location coordinating their "synchronization"
in time. Some stations may have special marshaling facilities to accumulate
vehicles. The speed will be set from 200 km/h (along the ascents and in
the tunnels) to 300...350 km/h along horizontal stretches and descents.
The line and central computers will control traffic by accumulating information
about the location, speed, destination and condition of all major units
(the running gear and the drive, in the first place) of each vehicle. Modern
control software allows to arrange the transport traffic of STS vehicles
with 100-percent safety without man's involvement.
A system similar to the one developed in Japan for the self-controlled
Mitsubishi car can be employed to control the STS vehicles. Each vehicle
will have three on-board TV, infrared and ultrasound systems running simultaneously.
The on-board computer will receive signals from the vehicles ahead to analyze
and adjust the proper speed and the spacing. Also, there will be mutual
information exchanges and with the line and central computer systems to
check the location, speed, condition of the route structure, supports,
switches, irregularities, track defects, etc. The on-board computer system
will employ microprocessors to process the data from built-in sensors,
TV and IR cameras, mechanical means. Relevant commands will be issued for
various executive mechanisms. The manoeuvring operations are automatically
coordinated with the route on-line computer system in order not to affect
the transport traffic.
1.7.4. Traveling Time
Table 3
Time spent by a passenger to travel from downtown Beijing
to downtown Hongkong (2,880 km)
|
Ser. No
|
Transportation process
|
Time, min at
|
travelling speed
|
|
|
|
300 km/h
|
400 km/h
|
|
1
|
Waiting for a vehicle to arrive
|
1
|
1
|
|
2
|
Boarding
|
2
|
2
|
|
3
|
Waiting until start
|
1
|
1
|
|
4
|
Joining the main traffic
|
1
|
1
|
|
5
|
Acceleration to 300 km/hour
|
2
|
3
|
|
6
|
Traffic along the route
|
574
|
429
|
|
7
|
Deceleration
|
2
|
3
|
|
8
|
Driving into the terminal
|
1
|
1
|
|
9
|
Landing
|
1
|
1
|
|
10
|
Unforeseen time losses
|
5
|
8
|
Total: 590 (9 hrs 50 min) 450 (7 hrs 30 min)
Time spent for travelling from other communities is shown in Table
4.
Table 4
Time spent by passengers for travelling from Beijing at
a speed 300 km/h
|
Station
|
Distance between stations, km
|
Time en route between stations, min
|
Time en route with incrementation
|
|
Beijing
|
|
|
|
|
Tjantzing
|
110
|
29
|
29 min
|
|
Tzinan
|
280
|
56
|
1 hour 25 min
|
|
Wejfang
Tzindao
|
180
130
|
36
26
|
2 hours 01 min
2 hours 27 min
|
|
Ljanyungan
|
230
|
46
|
3 hours 13 min
|
|
Duntaj
|
210
|
42
|
3 hours 55 min
|
|
Shanghaj
|
220
|
44
|
4 hours 39 min
|
|
Hanchzhou
|
160
|
32
|
5 hours 11 min
|
|
Ninbo
|
150
|
30
|
5 hours 41 min
|
|
Venchzhou
|
230
|
46
|
6 hours 27 min
|
|
Fuchzhou
|
220
|
44
|
7 hours 11min
|
|
Taibej
|
330
|
79
|
8 hours 30 min
|
|
Total:
|
2450
|
-
|
8 hours 30 min
|
1.7.5. Route Traffic Capabilities
When trains comprise 10 ten-seat vehicles moving with the speed
300 km/h with the interval 30 seconds, the traffic along a single line
during peak hours will amount to 12,000 passengers/h and 24,000 passengers
along the route (with two oppositely directed lines) or 576,000 passengers
every 24 hours pr 210 million passengers a year. There is still a margin
to increase the traffic without adding more lines.
The minimal distance between cargo modules along the line is 50
m (50...100 m is the minimal urgency deceleration by throwing out a braking
parachute), hence the ultimate traffic capacity of a single line at a speed
300 km/h is 24 thous. t/h or 576 thous. t/day (210 million t/year). The
maximum traffic capacity of a double-track line is 48 thous. t/h. 1,150
thous. t/day, 420 million t/year.
The actual scope of cargo and passenger traffic will be one order
of magnitude less because the route will operate at its 10-percent capacity,
it will promote the reliability and safety of the transport system in operation,
in the long run.
1.8. Safety and Reliability
1.8.1. Safety at Terminals
The safety of passengers is achieved by the synchronization of speeds
and the circular terminal platform, for example, by joining them with mechanical
means. The platform should move with the speed 0.4 m/s for the passenger
traffic of 2,000 passengers per hour with a full turn during 6.5 min (when
the outer diameter is 50 m).
Electrical safety is achieved by using safe electrical voltage (12
or 24 V) or batteries in vehicles, or electrical current of the same voltage
supplied through the rail track to exclude shock hazards.
1.8.2. Transport Line Electrical Safety and Reliability
Safety is ensured by a relatively small voltage in the line (about
1,000 V), insulation of current carrying rail heads and supports and by
non-conductive vehicle bodies made from composite materials. Hence, in
case a vehicle misses the rail track it will not produce any short-circuiting
between rail heads.
High-voltage electrical transmission lines (power cables with stronger
insulation) and low-voltage lines (12 or 24 V) will be connected in the
tunnel (along the sea route portions) to the rail heads connected to the
step-down transformers after every several kilometers. It will exclude
shock hazards for passengers in emergencies, for example in case of a failure
along the line when people can touch the live STS route structure.
When the traffic reaches 1,000 passengers per hour (24 thous. passengers
a day and cargo traffic 2 thous. t/h or 17.5 million t/year) along a leg
100 km long, 35 passenger vehicles and 170 cargo vehicles will run simultaneously
with the total power of motors 9,600 kW. No additional transmission lines
to supply the STS and its infrastructure are needed, because the rail-string
will allow to transmit the electrical power over 10,000 kW (up to 100,000
kW, if it has a special design). Therefore, the STS should be connected
to the existing grid every 100...300 km and more.
1.8.3. Traffic Safety
Traffic safety is achieved by failure-free operation of all the
systems effective to maintain the routine mode of traffic: the computerized
control means, reliable electronic systems, communication lines and measuring
instruments, executive mechanisms of switches and drive controls and the
braking system, reliable mechanical members of the route structure, STS
supports, etc. A hundred-percent safety of the traffic processes is evidenced
by the experience of operation of high-speed railways in the world. For
example, high-speed railways in Japan have transported over 5 billion passengers
during 20 years of operation without any accidents or casualties.
The STS employs four vehicle braking modes: routine (acceleration
is 1 m/s2, the braking path is 3,500 m), urgent (2.5 m/s2,
the braking path is 1,400 m), emergency (10 m/s2, 350 m) and
extreme (50 m/s2, 70 m). The emergency an extreme braking are
achieved by actuating all the braking systems, including parachutes provided
in each vehicle. Once the explosive charge ejects the parachute, safety
air cushions are inflated in the passenger salon to exclude lethal traumas
under the above loads ( the peak overloads will be approximately equal
to those experienced by car passengers in collisions with immovable obstacles
at a speed 25 km/h.
In case of power failure each vehicle is equipped with a battery
and an emergency starting motor which will deliver the vehicle at a slower
speed to one of the stations or emergency stop platforms on each anchored
support, i.e. after every 1...2 km.
If necessary, the sea portion can be run through solely on batteries
which can be recharged en route overland. In this case the route structure
will be dead.
1.8.4. STS Structural Reliability and Functioning
STS cable and string elements of rails and carrying structures are
exposed to the utmost strain. Since they are in the corrosion resistant
medium in the special sheath and in a mechanically strong body protecting
them against external effects, their service life can amount to hundreds
of years. Also, the traveling load alters the stress-strain state of these
elements only by one per cent (see [1], p. 8) and this state remains basically
unchanged during the entire period of operation extending the service life
and saving operation costs. Since the string elements are located in different
remote places (mutually isolated wires in the strings of the left and right
rails, the one-way and return lines, the upper and lower strings, etc.),
the probability that they snap simultaneously is close to zero, even in
case of disasters, such as earthquakes, floods, landslides, hostilities,
etc.). Even in case 90% of carrying wires snap, the structure will not
collapse, unlike other structures, such as bridges, highway loops, viaducts,
modern skeleton buildings, etc.
The STS route structure remains highly durable even when destroyed
by terrorists. A support is secured to the route structure with a special
unfastening mechanism which releases it making just the rail-string span
longer and increasing its corresponding deflection. It will not destroy
the integrity of the route even in the case when several supports in line
are destroyed.
The results of a model of the STS vehicle tests in the aerodynamic
tube at a speed 250 km/h at the Central Research Institute named after
the Academician A.N. Krylov (Saint-Petersburg) have manifested that lateral
winds blowing with the speed within 100 km/h produce lateral capsizing
forces within 100 kgf. They will not affect the functioning of the transport
system, the more so they will not derail vehicles.
1.8.5. Ecological Safety
The STS transport system is highly safe ecologically both during
erection and in operation.
The STS can be erected without any special equipment (such as platforms
or construction power shovels) without using road approaches because the
necessary materials and structural members will be delivered along the
erected route stretches. Also, erection may obviate the need of earthwork
destroying the soil level or the humus accumulated during millions of years,
because the supports will be erected on posts driven into land as foundations.
these features are extremely essential when the route runs over fertile
or most valuable plots of land.
The STS will consume electricity for its operation as an ecologically
clean source of energy. Passenger vehicles and transport modules will be
airtight and they can stop only at special stations, it will eliminate
contamination of the environment by passengers or any other sorts of industrial
waste. the containers are designed to exclude leaks (they will have no
pumps, valves, seals and other joints which may leak) or losses of bulk
cargoes. Any crush along the route may cause derailing of just a single
module (the extreme braking path of the next module will be less than the
distance between the two), also a parachute will be activated to decelerate
the container so that it does not disintegrates when it drops on the land
surface.
The STS needs no embankments, cuttings, tunnels , bridges or conduits.
One carrying support occupies just one square meter, the anchor support
occupies 10 square meters. Hence, one kilometer will require the area less
than 100 square meters, i.e. 0.01 hectare, therefore the conventional land
alienation will be within 10 cm. It is much less than the area occupied
by a walking path.
The length of a span is not critical because both forests or individual
trees along the route may remain because any support can be shifted this
or that way straight during construction.
The STS route will not interfere with the migration of soil and
surface water, animals, reptiles, crop growing or any other land use.
The STS will be a low-voltage line, so it will not create any electromagnetic
interference and it can pass quite high (up to 100 m) over residential
buildings, crop land, over game preservations and parks. Absence of sliding
electrical contacts in the vehicle-contact grid couples (unlike railways)
and the power of the motors exclude radio noise.
The STS requires extremely few materials for its erection, therefore
it will be ecologically clean in this respect. For example, a single-track
route as long as a railway can be erected from the materials of just a
single rail and each third sleeper (the railway has still the second rail
and 2/3 of sleepers, the contact grid, rail conduits, viaducts, etc.).
Hence, the STS for its erection will not require as many blast furnaces,
ore, mines (to produce steel, copper), cement and reinforced concrete plants
, earth, sand and gravel quarries, the scope of deliveries by trucks and
by railway cars of the materials, special approaches, etc., which would
incur an additional, sometimes irreversible ecological damage.
The STS vehicle has no projecting parts, excepting narrow wheels
protruding for 10 cm from the body. It needs no windshield wipers or lights
(because there is no driver) which produce noise at high speeds. The wheels
can be fabricated from light alloys (the load per wheel is 500...1500 kgf),
therefore they can weigh within 10...20 kg. Hence, a STS train weighs hundreds
of times less than a railway train, it is tens of times shorter and runs
much smoother because of the track smoothness (what can be more straight
than a strongly tensioned string?). Therefore, the STS train will produce
hundreds of times less noise and vibration than high-speed trains.
1.9. Attractive Appearance and Comfort
The majority of the people spend their active time within a closed,
limited space. Due to the ergonomics the common transport means allow to
see some land surface, a portion of the road, etc.
The STS both solves the problems of comfort and its functional objective
to fast deliveries of passengers to their destinations. Large windows,
comfortable seats, soft silky tracks transform a common trip into the delight
of enjoying the sights of nature from the birds' flight.
The appearance of slim route structures, support and stations will
fit into the natural landscape without impairing the ecology or destroying
even fine natural components and the historical architectural styles along
the route adding islands of modern architectural shapes.
Each vehicle will be air conditioned, passengers will enjoy a broad
variety of other services, multichannel music and TV, world telephone communications,
special services for businessmen, passengers with children, disabled people.
The STS vehicles are airtight equipped with a system of pressurized or
chemical water closets to accumulate waste.
Passengers can command vehicles to stop at any intermediate station,
i.e. after every 15...20 minutes.
1.10. Construction Process
The string prepared in advance is stretched to a certain tensioning
(the force of tensioning or elongation in tensioning serve as a reference
parameter) and its ends are secured rigidly, for example, by welding, to
anchor supports. the intermediate supports are erected beforehand or in
the process of tensioning or after. A platform is sent along the intermediate
supports and the string which can travel independently and fix its position
rigidly in respect to the supports The hollow rail body is mounted with
the help of the platform span after span, then it is fixed in the specified
position and filled with a filler the rail head, the cross plank are erected
and other necessary operations are performed to erect the route structure.
All these operations are easily mechanized and automated, they can be performed
during 24 hours every day in any weather to expedite construction reducing
labor consumption and cost. To eliminate microroughnesses and microwaviness
of working surfaces after the rail head is erected and to remove gaps between
its joints the system can be polished throughout its length.
The STS can be erected with a special erection combine which tensions
the string and other tensional rail members over the combine rather than
over the anchor support. the combine moves along the route on its walking
legs and places assembled intermediate supports with the ready rail track,
once it reaches the anchor support it fastens them together securely.
Since the diameter of underwater tunnels is small (3.2 m) more advanced
techniques can be employed instead of those currently used. Ready route
portions can be fabricated in dry docks by continuous concreting. the docks
can be placed along the coast, then the ready route legs will be floated
to the site of erection. If floating docks are used that tunnels can be
fabricated at sea and then the ready portions can be lowered to the prepared
(leveled) sea bottom.
The assembled tunnels are placed on the sea bottom with zero buoyancy
to exclude cross strains which can make their longitudinal axis curvilinear.
Because of this reason and due to a high bending ridigity of the tunnels,
significant longitudinal tensioning strains during erection, the ready
route legs lie down on the bottom irrespective of its relief in a flat
manner with smooth bends (the curvature radius is over 10 thous. m). Hence,
no need to prepare the sea bed sites too thoroughly the equilibrium position
of the tunnels is fixed by covering them with a layer of soil, for example
by hydrowashing. Since tunnels are buoyant and weightless, the dynamic
loads in operation are insignificant (short, lasting one tenth of a second,
load amounting to 3...6tf with the periodicity of several tens of seconds),
they need no foundations. Due to a high bending rigidity of the tunnels,
the dynamic load will distribute over a large area producing an extremely
low pressure, under 0.01 kgf/cm2.
1.11. Feasibility Parameters
Tables 5 and 6 introduce the feasibility parameters of the overland
and sea portions of a double-track route 1 km long, respectively, Tables
7 and 8 show their total costs.
The following aggregate prices were used to evaluate the cost of
structures: metallic structures depending upon their complexity and steel
grade - 1,500...5,000 US $/t; aluminium structures - 5,000 US $/t; reinforced
concrete structures - 750...1,000 US $/m3, US$ 500 per cubic meter of monolith
reinforced concrete (for the sea portion). Fifteen intermediate stations
have been projected each US$ 5 million. The cost of terminals (17) and
service buildings was estimated 3,000 US $ per m2 of the area
(general construction works plus engineering and technological equipment),
1,500 US $/m2 of the area of garages (workshops) and 1,000 US $ per sq.m
of the territory of cargo terminals (12).
The cost of a double-route track will be US$ 1.1 million for the
overland portion and 8.7 million for the sea portion per km, the total
of the complete 3,140 km route together with its infrastructure is US$
6,400 millions, including 4,800 million for the overland portion (3,000
km) and 1,600 million for the sea portion (140 km).
Table 9 lists the major feasibility indicators, Table 10 lists the
costs of transportation (the cost of transportation of one passenger and
a ton of cargo). The following parameters unlisted in the Tables were used
for the estimates: cost of electrical energy - 0.05 US $/kW x h; returns
yielded by the transport system: 80% from the passenger traffic and 20%
from the cargo traffic.
The cost of transportation of a passenger over a distance of 2,880
km from Beijing to Hongkong at an average passenger traffic 50,000 passengers
during 24 hours will amount to 30.63 US$, one ton of cargo (at 100,000
tons during 24 hours) will cost 9.55 US$. The transport system will yield
a profit of 340 mln US$ a year.
The profit can be increased significantly by raising the price of
tickets to 70 US$ (the price of railway tickets). It will yield an additional
profit of 660 mln US$ (at 50,000 passengers during 24 hours). The transport
system will pay back its cost during 6.4 years. With passenger traffic
100 thous. per day the route will pay back within 3 years. Cheap traffic
along the transport system is due to its low cost (below the cost of a
railway of the same length) and insignificant specific energy consumption
for traction (for example, a STS vehicle, under other equal conditions,
is cheaper than a car 12 times when estimated per passenger, including
3 times due to improved aerodynamics, 2 times due to a greater efficiency
of the motor and 2 times due to a greater passenger capacity) because a
10-seat vehicle can reach the speed 300 km/h with a motor just 80 kW. Also,
it has been projected that the entire route will be self-sufficient for
80% from passenger traffic, therefore to deliver a ton of crude from mainland
China to Taiwan will be cheaper than along a pipeline. The cost of transportation
can be reduced still more if individual power plants are erected along
the route which can generate energy cheaper than 0.05 US$/kW envisaged
by the project.
A high passenger and cargo traffic is possible along the route because
it will link the regions of China in which several hundreds of millions
of people live, short traveling time (with the average distance between
the cities along the route 200 km, the average traveling time between them
is 40 min), cheap trips allow to make one-day business trips and mutual
visits of tourists, businessmen, shoppers, etc.; it will allow many people
to go to jobs from one communities to another along the route. It will
make car tourism cheap, because personal can be delivered, for example,
from Hongkong to Beijing (2,880 km) at a cost just US $ 20 within 10 hours.
Table 5
Consumption of materials and cost of one km overland portion
of a double-track route
|
Structural
|
Material
|
Consumption of materials per km
|
Tentative cost,
|
|
element
|
|
mass,
tons
|
volume,
m3
|
Thous. US$ per km
|
|
1. Rail-strings. total
|
|
|
|
450
|
|
Including:
1.1 Heads
|
Steel
|
96
|
-
|
190
|
|
1.2. Body
|
Al sheet
|
5
|
-
|
25
|
|
1.3. String
|
Steel wire
|
79
|
-
|
160
|
|
1.4. Filler
|
Composite
|
-
|
45
|
20
|
|
1.5. Gluing wax
|
Composite
|
1
|
-
|
10
|
|
1.6. String protective sheath
|
Polymer
|
4
|
-
|
20
|
|
1.7. String water insulation
|
Polymer
|
2
|
-
|
10
|
|
1.8. Others
|
|
-
|
-
|
15
|
|
2. Cross plates
|
|
-
|
-
|
20
|
|
3. Intermediate supports (15 m tall), total
|
|
-
|
-
|
190
|
|
Including:
3.1. Posts
|
Reinforced Concrete
|
-
|
96
|
70
|
|
3.2. Cross pieces, stay guys
|
Reinforced concrete
|
-
|
46
|
35
|
|
3.3. Support upper structures
|
Steel
|
8
|
-
|
20
|
|
3.4. Pile foundation
|
Reinforced concrete
|
-
|
48
|
48
|
|
3.5. Others
|
|
-
|
-
|
17
|
|
4. Anchored supports (15 m tall), total
|
|
-
|
-
|
105
|
|
Including
4.1. Support bodies
|
Reinforced concrete
|
-
|
50
|
38
|
|
4.2. Pile foundation
|
Reinforced Concrete
|
-
|
36
|
36
|
|
4.3. Metallic structures
|
Steel
|
2
|
-
|
5
|
|
4.4. Anchor fixtures
|
Steel
|
2
|
-
|
10
|
|
4.5. Others
|
|
-
|
-
|
16
|
|
5. Earthwork
|
|
-
|
-
|
20
|
|
6. Rail power supply system
|
|
-
|
-
|
40
|
|
7. System to monitor the conditions of supports and route
structure
|
|
-
|
-
|
10
|
|
8. System to monitor transport traffic
|
|
-
|
-
|
20
|
|
9. Emergency power supply system
|
|
-
|
-
|
20
|
|
10. Transport traffic control system
|
|
-
|
-
|
30
|
|
11. Emergency stop points
|
|
-
|
-
|
20
|
|
12. Surveying and mapping
|
|
-
|
-
|
50
|
|
13. Cost of land and its preparation
|
|
-
|
-
|
50
|
|
14. Other tasks
|
|
-
|
-
|
25
|
|
15. Unforeseen expenses
|
|
-
|
-
|
50
|
|
|
|
|
|
|
|
TOTAL:
|
|
|
|
1100
|
Table 6
Averaged consumption of materials and cost of
one km sea portion of a double-track route
|
Structural
|
Material
|
Consumption of materials per km
|
Tentative cost,
|
|
element
|
|
mass,
tons
|
volume,
m3
|
Thous.. US$ per km
|
|
1. Rail-strings. total
|
|
|
|
450
|
|
Including:
1.1 Heads
|
Steel
|
96
|
-
|
190
|
|
1.2. Body
|
Al sheet
|
5
|
-
|
25
|
|
1.3. String
|
Steel wire
|
79
|
-
|
160
|
|
1.4. Filler
|
Composite
|
-
|
45
|
20
|
|
1.5. Gluing wax
|
Composite
|
1
|
-
|
10
|
|
1.6. String protective sheath
|
Polymer
|
4
|
-
|
20
|
|
1.7. String hydroisolation
|
Polymer
|
2
|
-
|
10
|
|
1.8. Others
|
|
-
|
-
|
15
|
|
2. Tunnels (three), total
including:
2.1. Tunnel body
2.2. Insulation sheath
2.3. Protective sheath
2.4. Hydroisolation
2.5. Emergency passenger and
cargo evacuation system
2.6. Emergency water tightness
and water pumping system
2.7. System of fixture of the
route structure in the tunnel
2.8. Others
|
Reinforced concrete
Glass plastic
Glass plastic
Composite
|
-
-
60
720
48
-
-
-
-
|
-
8850
-
-
-
-
-
-
-
|
6900
4425
300
1080
240
250
200
100
305
|
|
3. Earthwork
|
Loose soil
|
-
|
80000
|
400
|
|
4. Rail power supply system
|
|
-
|
-
|
150
|
|
5. System to monitor the conditions of the tunnel and
the route structure
|
|
-
|
-
|
80
|
|
6. System to monitor transport traffic
|
|
-
|
-
|
20
|
|
7. Emergency power supply system
|
|
-
|
-
|
60
|
|
8. Transport traffic control system
|
|
-
|
-
|
50
|
|
9. Emergency stop points
|
|
-
|
-
|
100
|
|
10. Surveying and mapping
|
|
-
|
-
|
50
|
|
11. Cost of land and its preparation
|
|
-
|
-
|
50
|
|
12. Other tasks
|
|
-
|
-
|
100
|
|
13. Unforeseen expenses
|
|
-
|
-
|
290
|
|
|
|
|
|
|
|
TOTAL:
|
|
|
|
8700
|
Table 7
Cost of a double-track STS transport line
‘Beijing-Hongkong (Taibej)’, sea portion (across the Taiwan
Straight, 140 km)
|
Ser. Nos
|
Description of route elements
|
Q-ty, volume
|
Item cost, thous. US$
|
Total cost, mln US$
|
|
1
|
Way structure
|
140 km
|
450
|
63
|
|
2
|
Supports
|
140 km
|
690
|
966
|
|
3
|
Earthwork
|
140 km
|
400
|
56
|
|
4
|
Rail power supply system
|
140 km
|
150
|
21
|
|
5
|
System for monitoring the condition of the way structure and the tunnel
|
140 km
|
80
|
11.2
|
|
6
|
Control system of transport traffic
|
140 km
|
20
|
2.8
|
|
7
|
Emergency power supply system
|
140 km
|
60
|
8.4
|
|
8
|
Transport traffic control system
|
140 km
|
50
|
7
|
|
9
|
Emergency stop platforms
|
140 km
|
100
|
14
|
|
10
|
Surveying
|
140 km
|
50
|
7
|
|
11
|
Cost of land and its preparation
|
140 km
|
50
|
7
|
|
12
|
Research and development
|
-
|
-
|
20
|
|
13
|
Pilot STS leg
|
1 km
|
20000
|
20
|
|
14
|
Other elements of the route infrastructure
|
-
|
-
|
100
|
|
15
|
Other tasks
|
-
|
-
|
100
|
|
16
|
Unforeseen expenses
|
-
|
-
|
196.6
|
TOTAL: 1600
Table 8
Cost of a double-track STS transport line
‘Beijing-Hongkong (Taibej)’, overland portions (3,000 km)
|
Ser. Nos
|
Description of route elements
|
Q-ty, volume
|
Item cost, thous. US$
|
Total cost, mln US$
|
|
1
|
Way structure
|
3000 km
|
470
|
1410
|
|
2
|
Supports
|
3000 km
|
295
|
885
|
|
3
|
Terminals
|
17
|
30000
|
510
|
|
4
5
|
Intermediate stations
Garages and workshops
|
15
8
|
5000
15000
|
75
120
|
|
6
|
Earthwork
|
3000 km
|
20
|
60
|
|
7
|
Rail power supply system
|
3000 km
|
40
|
120
|
|
8
|
System for monitoring the condition of the supports and the way structure
|
3000 km
|
10
|
30
|
|
9
|
Transport traffic control system
|
3000 km
|
20
|
60
|
|
10
|
Emergency power supply system
|
3000 km
|
20
|
60
|
|
11
|
Transport traffic control system
|
3000 km
|
30
|
90
|
|
12
|
Emergency stop platforms
|
3000 km
|
20
|
60
|
|
13
|
Surveying
|
3000 km
|
50
|
150
|
|
14
|
Cost of land and its preparation
|
3000 km
|
50
|
150
|
|
15
|
Research and development
|
-
|
-
|
25
|
|
16
|
Pilot double-track STS leg
|
20 km
|
2000
|
40
|
|
17
18
|
Other elements of the route infrastructure
Cargo terminals
|
-
12
|
-
20000
|
200
240
|
|
19
|
Other tasks
|
-
|
-
|
200
|
|
18
|
Unforeseen expenses
|
-
|
-
|
315
|
TOTAL: 4800
Table 9
Engineering and Economic Indicators of the STS double-track
Beijing-Hongkong (Taibej) Line
|
Parameter
|
Magnitude
|
|
|
|
|
1. Transport line characteristics
|
|
|
1.1. Total cost, million US$
|
6400
|
|
1.2. Depreciation deductions, , %
|
5
|
|
1.3. Annual operation cost & cost of maintenance and routine repairs,
thous.US$
|
20
|
|
1.4. Term until fully repaid, years
|
20
|
|
1.5. Route stretch, km
|
3140
|
|
|
|
|
2. Vehicle characteristics
|
|
|
2.1 Cost, thous. US$:
- passenger
- cargo
|
30
10
|
|
2.2. Number of seats:
- business class
- first class
- deluxe
|
10
5
1
|
|
2.3. Carrying capacity, kg:
- passenger
- cargo
|
2000
4000
|
|
2.4. Transport module weight (net), kg
|
1500
|
|
2.5. On-line utilization factor
|
0,75
|
|
2.6. Reserve park of vehicles, %
|
20
|
|
2.7. Average annual speed, km/hour
|
300
|
|
2.8. Engine power. kW:
- passenger
- cargo
|
80
40
|
|
2.9. Vehicle annual run along 2,880 km leg, thousand km:
- passenger
- cargo
|
1720
1720
|
|
2.10. Annual transportation volume
by one transport module (along a 2,880 km leg):
- passengers
- cargo, tons
|
5980
2390
|
|
2.11. Specific power losses for traction:
- passenger, kW x h/ passenger x km
- cargo, kW x hour/ton x km
|
0.027
0.033
|
|
2.12. Depreciation deductions, %
|
10
|
|
2.13. Annual operation cost, %, versus vehicle cost
|
10
|
|
2.14. Term until repaid, years
|
10
|
Table 10
Cost of Transportation along ‘Beijing-Hongkong (Taibej)
Line,
the Beijing-Hongkong stretch (2,880 km)
|
|
Scope of transportation (both ways)
|
|
Parameter
|
passengers,
thousands/day
|
cargo,
thous.tons/day
|
|
|
20
|
50
|
100
|
50
|
100
|
200
|
|
1. Reduced costs 2,880 km leg):
- US$/pass.
|
76.02
|
33.63
|
19.51
|
-
|
-
|
-
|
|
- US$/ton of cargo
|
-
|
-
|
-
|
13.08
|
9.55
|
7.77
|
|
1.1. Costs along the transport line, total
|
70.63
|
28.24
|
14.12
|
7.07
|
3.54
|
1.76
|
|
Including:
- depreciation deductions
|
32,16
|
12,86
|
6,43
|
3,22
|
1,61
|
0,80
|
|
- operation cost
|
6.31
|
2.52
|
1.26
|
0.63
|
0.32
|
0.16
|
|
- deductions for profit
|
32.16
|
12.86
|
6.43
|
3.22
|
1.61
|
0.80
|
|
1.2. Cost of vehicles, total
|
5.39
|
5.39
|
5.39
|
6.01
|
6.01
|
6.01
|
|
Including:
- depreciation deductions
|
0.50
|
050
|
0.50
|
0.42
|
0.42
|
0.42
|
|
- operation cost
|
0.50
|
0.50
|
0.50
|
0.42
|
0.42
|
0.42
|
|
- deductions for profit
|
0.50
|
0.50
|
0.50
|
0.42
|
0.42
|
0.42
|
|
- energy cost
|
3.89
|
3.89
|
3.89
|
4.75
|
4.75
|
4.75
|
|
2. Number of vehicles for the entire route, at average transportation
stretch 2,880 km) pcs
|
1,220
|
3,050
|
6,100
|
7,630
|
15,260
|
30,520
|
|
3. Rolling stock cost , US$ million
|
36.6
|
91.5
|
183
|
76.3
|
152.6
|
305.2
|
|
4. Average traffic interval between vehicles (single vehicles along
one line)
- seconds
|
86.4
|
34.6
|
17.3
|
13.8
|
6.9
|
3.4
|
|
- spacing, km
|
7.2
|
2.9
|
1.4
|
1.15
|
0.58
|
0.29
|
2. Comparison of the STS Performance and Economics
with other High-Speed Route alternatives
2.1. General
The STS performance is better to compare with railway, automobile,
air transport means and magnetic suspension trains, since the major competitors
of the STS will be automobiles and traditional high-speed railways.
In all these cases a great significance should be attached to the
specific consumption of electrical energy for transportation. STS transport
modules have a comparatively small specific energy consumption in motion.
For example, at speeds 300 km/h: 0.027 kWxpass/passxkm
for passenger and 0.033 kWxh/txkm
cargo traffic. High efficiency of STS motors, small energy losses in motion
(good aerodynamics and low mechanical losses when a rigid wheel runs over
a rigid track) make the STS transport the most economical among the existing
types of high-speed transport means running with the same speeds. compared
with high-speed railways in the same measures the consumption of energy
is reduced 5 times, compared with magnetic suspension trains 10 times and
compared with jet planes 20 times.
The STS route requires less materials, therefore it is cheaper.
For example, to erect the carrying portion an insignificant amount of reinforced
concrete is required - 280 m3/km for a double-track route with
supports 15 m tall. About 500 m3/km is required if its consumption
for stations and auxiliary systems is added. For comparison: consumption
of reinforced concrete just for enclosures high-speed railways and routes
of magnetic suspension trains is 750 m3/km.
Since the scope of earthwork is little, so are the expenses. The
STS route can run without embankments or excavations along any terrain.
Earthwork will have a localized nature (drilling of holes for supports
totally 100-200 m3/km, or not earthwork is required at all in
case the foundation is erected on piles. For comparison, to construct a
kilometer of a modern motorway or railway requires to 10,000...50,000 m3,
100,000 m3 in cross country or mountainous places.
The consumption of other structural for the route and supports is
as small, because cheap, available, mass-produced materials will be used.
The STS rolling stock cost can be estimated in comparison with passenger
cars which are the closest analogs in dimensions and designs.
Mass produced electric motors 25.50 kW are 1.5...2 times cheaper
than internal combustion engines of the same power, they are more reliable,
durable, easier to operate and maintain.
The STS transport module body will cheaper than a car body of the
same size because of its simpler design (absence of radiators, doors, baggage
space, front hood, lights, dimensional, braking and other warning lights,
windshield wipers, windows lifting mechanisms, etc.).
The STS vehicle will have a cheaper and simpler running gear and
suspension (no unreliable and expensive tires, wheel turning mechanisms,
simpler torque transmission to stationary wheels, no problems with tractability,
etc.).
The r.p.m. and torque control systems of these two transport means
cost are approximately similar and are as intricate (it is a motor r.p.m.
control unit in the STS and the gear box, clutches, fuel injection system,
etc, in cars).
The vehicle steering system is much simpler and cheaper than in
cars, because there will be few parameters: the speed, spacing between
vehicles and location (the coordinate) of a vehicle along the line. Irrespective
of the computer technology progress it is still complicated to steer a
car, so far only human brain can tackle the problem (the driver factor
should be considered when evaluating the cost of running a car: at present
hundreds of millions have to drive cars for hours daily with their own
daily shortage of time). A cheap controller with its own control software
will tackle the problem with the STS controlled and guided by on-line computers
integrated into a net. To control a car, in addition to servomechanisms
(the steering wheel and its mounting, wheel turning mechanism, gas, brake
and clutch pedals, gear mechanism, etc.) a whole system is required to
visualize information for steering which is unnecessary with the STS, such
as windshield wipers with their actuating mechanisms and detergent delivery
system (to keep the windshield clean and to ensure proper visibility),
main and auxiliary lights, instrument panel, mirrors, horn, etc..
The STS vehicle will have about the same exterior and interior as
a car and can be widely variable in response to individual tastes.
Also, the STS vehicle has no fuel tank (thus, no gas filling stations
along the route, refineries providing gasoline and diesel fuel, oil wells
are required); it does not require any system of removing and additional
combustion of exhaust (for example, more strict ecological norms in many
countries have recently made cars much more expensive).
Considering the above argumentation it can be predicted that mass
produced STS vehicles will be 1.5...2 times cheaper than passenger cars
of the same capacity, thus, it will be easier available (in future the
STS advantages may lead to the creation of a wide string transport net
comparable with the current network of motorways).
2.2. High-Speed Railways
High-speed railways (HSRW) designed for speeds 250...300 km/h are
becoming more and more popular in the world. Their extension has gained
priority in the transport, for example, the Council of Ministers of the
European Community projects to invest about 300 billion ECU (until the
year 2010) into their construction.
The common railway transport is not suitable for high speeds. Moreover,
the earth bed subsidence should not exceed 1 mm, hence loose soil should
be removed to a depth of several meters to erect such railways. As a rule,
loose soils occupy lowlands, flooded lands, marshy land, which are a natural
water system accumulating and distributing moisture among rivers. Back-filling
(and compacting) in great volumes will impair the natural water flow with
a serious risk of dehydration of some territories, swamping of others,
losses of forested lands, arable and crop fields, etc. In fact, the high-speed
route embankments will become a dike (a dam) for soil and surface water.
Also, such lines will require a special enclosure (from both sides) and
noise screens to fence off wild and home animals, agricultural activities,
etc. In general, a high speed line will require 3.2 hectares/km (the data
for Germany), the entire route will require 9600 hectares of rather expensive
land to be vacated. Moreover, there is no worldwide experience of erecting
the HSRW in the seas. Hence, its erection over the Taiwan Straight 140
km wide is highly problematic and would be too expensive (30...40 billion
US$).
A high-speed train is a rather strong source of noise and soil vibrations,
which is not surprising with its weight of hundreds of tons, its length
of hundreds of meters and locomotion consuming thousands of kilowatts.
The train has a great variety of projecting pieces, connectors, joints
each acting as a noise source. One wheel pair weighs about a ton, it would
sure hit against microroughnesses, letting alone macroroughnesses of rail
joints, for example.
The major disadvantage of high speed railways is their cost. For
example, experts of the European Bank of Reconstruction and Development
have evaluated that a high-speed route between Saint-Petersburg and Moscow
(660 km) will cost 6...8 billion US $, transportation of a single passenger
will cost 123 US$ (approximately as much as along European high-speed routes).
The overland routes between Beijing-Hongkong (Taibej) may be estimated
to cost 30...40 billion US$, the cost of transportation over 2,880 keg
will be 500 US$. These figures exceed 5...10 times those for the STS.
The means required for erection of just overland high-speed railway
routes “Beijing-Honkong (Taibej)” would be sufficient to construct complete
STS routes over 15 thousand kilometers long.
2.3. Analysis of Motor Transport Capabilities
The automobile transport is known to be unable to compete with railways
and air transport at distances above 200...400 km and more serving as a
complement of the integral transport system.
Lack of competitiveness of the automobile transport as a major means
of the future passenger and cargo traffic along the Beijing-Hongkong (Taibej)
route is apparent due to the following reasons:
- even erection of a new multilane motorway will not truly increase
the speed and the comfort of the automobile transport which will be much
less than that of the STS with an average speed of a passenger car being
below 100...110 km/h, the buses will be still slower. It means that the
time needed to reach from downtown Beijing to downtown Hongkong will be
at least 28...30 hours, while an STS vehicle covers the distance within
9 hours and 50 minutes (within 7 hours 30 minutes at 400 km/h);
- erection of such motorway (with the account of dividing strips,
multiple loops at various elevations of the "clover leaf" types,
acceleration and deceleration strips, parking lots for rest, etc.) will
require a strip 2.5...3 times wider than a high-speed railway for the same
passenger traffic or 750...900 (!) than for a STS;
- exhaust into the atmosphere by the STS will be less than the HSRW
with its 0.6 gramms per passenger-kilometer, or automobiles with their
more than 10 gramms per passenger kilometer;
- the STS vehicles will be airtight with all the waste collected
and dumped at depots. Experience manifests that the strip along motorways
is most exposed to waste disposed by car passengers;
- erection of a multilane motorway across the sea will be extremely
costly, 20...30 billion US$, while the same STS route will cost just 1.6
billion US$.
2.4. STS versus Aviation
The STS is advantageous when compared with the air transport due
to the following considerations.
Research of transport means has allowed to discriminate clearly
between the competitiveness of the air and railway transport. The so-called
"transport niches" are implied defining the range of distances
and speeds at which a transport means provides passengers with the utmost
comfort and speed all with the least energy losses.
The analysis includes whether the absolute speed of transport means
is essential for passengers or the time to reach an airport or a railway
station, waiting until departure, baggage handling or the actual time of
traveling. The distance is estimated between destinations as the so-called
"zones of equal accessibility" located downtown. Hence, for example,
an air passenger needs 5...7 hours to travel from downtown Beijing to downtown
Hongkong (2000 km), i.e. almost the same time as with the STS traveling
at 400 km/h (7 hours 30 minutes).
However, the ecological safety is the governing factor in all these
comparisons. Modern airplanes release totally 300...400 g/passenger-kilometer
or 500...600 times more harmful substances into the atmosphere than the
high-speed railways or the STS, respectively. Actually, this parameter
is expected to reduce 3...5 times when aviation switches over to the double-contour
turbojet engines.
The major share of the exhaust accumulates exactly in the vicinity
of airports, i.e. around large cities when planes fly low and the engines
are boosted.
At low and medium altitudes (up to 5,000...6,000 m) the atmospheric
pollution with nitrogen and carbon oxides persists for several days, after
that they are trapped by moisture and produce acidic precipitation.
Aviation is the sole pollutant at higher altitudes with the harmful
substances persisting in the atmosphere much longer, about one year. Even
conversion to hydrogen engines fails to solve the problem. Harmless releases
of the engines as water vapors close to the land surface convert into ice
crystals shielding land.
Moreover, the noise effect is specifically strong around airports
and electromagnetic noise around radar stations.
It is an important factor to consider that airports require land
areas comparable with those for high-speed railways, yet these areas are
located straight near cities implying that they are more valuable.
A significant disadvantage of the air transport is that passengers
and cargo are delivered exceptionally to one terminal, while STS train
can deliver them to any intermediate station (the route may pass through
100 terminals and stations, or more).
The major factor is the travel cost which will exceed many times
that of the STS when the cost of traveling to the airport and back is added.
Thus, the Beijing-Hongkong future passenger and cargo traffic lines
manifest obvious advantages of the string transport routes.
2.5. Applicability of Transport Means with Magnetic Suspension
Magnetic suspension transport (MST) requires solution of sizable
scientific and engineering problems. Actually, the MST is still being experimented
upon, though a number of countries have erected separate short stretches.
Alternatives of implementation of the “Transrapid” System (FRG) and electrodynamic
suspension and linear synchronous motors have been evaluated, they require
to employ the effect of superconductivity. The MST requires 4...5 times
more investment than high-speed railways and 30...50 times more than the
STS. For example, the projected Transrapid route Berlin-Hamburg (Germany)
300 km long is estimated to cost 19 billion DM. Hence, a MST just overland
route Beijing-Hongkong (Taibej) may be estimated to cost 100...120 billion
US$, or 150...200 billion US $ with the account of the sea portion.
This amount is enough to erect complete STS routes about 100 thous.
km long.
3. Stages of Implementation of the STS Project
The primary objective is to complete research and development (25
million US$) to select, optimize and adapt to the terrain relief and operation
conditions of design, technological, engineering and other solutions, the
know-how accumulated by the author during 15 preceding years and the specialists
which he attracted to cooperate and then at the “NTL Transportlinien GmbH
(Germany) and since 1997 at the Research Center “JUNITRAN” (Belarus), because
it received the non-material assets accumulated during this period: patents,
know-how, engineering knowledge, designing, technological and other achievements
and their cost exceeds 1 billion US $, according to the estimate of the
Institute of Independent Assessment of Investment and Credited Projects
(Minsk). The program had been elaborated to develop the design of the transport
line and the vehicle (with all their components) with the account of wages
of designers and other staff, the cost of materials and standard pieces,
equipment, expenses to attract contractors, etc. The program is for the
conditions in the Republic of Belarus, but it can be easily adapted to
the conditions of any other country with the help of correction factors.
A special designing bureau should be created together with several
laboratories (to investigate motion dynamics; control, communications and
safety systems; electric motors and power supply and reliability of structures)
and major services (the general designer, the chief economist, the chief
process engineer, the chief engineer, the chief construction engineer,
the chief power engineer, the chief communications expert). This stage
can be accomplished within 2...3 years providing the corresponding finances
become available and 100...120 designers are recruited. Research and development
can be combined with the erection of a pilot STS leg 10...20 km long.
Then the pilot route leg (40 million US$) should be erected and
pilot vehicles should be fabricated (2 million US$). With sufficient finances
it can be accomplished within 2...3 years. The pilot leg can be erected
in any country where investors believe their investments can enjoy protection
and the designer can be sure of the proper protection of the intellectual
property and the copyright. A special research and designing center should
also be established in this country.
The route survey can be started parallel to the erection of the
pilot leg as well as the survey of other transport lines if there are clients
for such projects. It will allow to become leaders of the world super high
speed transport market in the 21-st century.
Development, designing and erection of the STS “Beijing-Hongkong
(Taibej)” can be started as implementation of the national transport programs
in mainland China and the island of Taiwan. In the process of implementation
of the national programs a unified line can be coordinated for constructing
the route, to elaborate design, technological and operational standards.
Then each country can independently erect its own portion of the transcontinental
route with its ramification (if necessary). After that, in future, the
route can on one side be extended to Western Europe and on the other side
to Indonesia.
The STS, due to its strong competitiveness, will be able to conquer
the markets of high-speed communications. It will create a new economic
niche by forcing out high-speed railways, trains with magnetic suspension
and aviation.
Appendices:
[1] “String Transport Systems on Earth and in the Space”
/ A.E. Junitsky, 337 pp., ill., Gomel, 1995.
[2] Information Materials on____ pages.
Ó A.E. Junitsky, 1997
General Designer of the STS Program
Back to the first page Junitsky ll
back to the first page of Discovery for Sale
(c) 1997 WWW Belarus, Minsk,
Belarus
Click Here
to Return Back
Webmasters,
contact Belarus.net support
Click Here
to visit Belarus.net